OTIF and Order Backlog: Measuring Whether You Keep Delivery Promises

Ask a sales team how deliveries are going and the answer is usually “mostly fine”. Ask the customer and the answer is often different, because the customer remembers the late and short deliveries, not the average. OTIF – on time, in full – is the measure that puts both sides on the same number. It counts an order line as a success only when the full quantity arrived by the promised date. Together with a clear view of the order backlog, it tells the plant whether it is keeping its promises and where the next failure is coming from. This guide explains how to calculate both, with a worked example.

What OTIF measures

OTIF % = order lines delivered on time and in full / order lines due x 100. A line is on time when it is delivered on or before its committed date (or within the window agreed with the customer), and in full when the delivered quantity is at least the ordered quantity (or within an agreed tolerance). A line that is on time but short, or complete but late, is a failure. That strictness is the point: it measures the experience of the customer, not the average of the plant.

Line, order or quantity?

Pick one definition, write it down, and use the same one every month and with every customer. When a large customer measures you with its own definition, track that one as well, because it is the figure in their supplier rating.

Worked example: eight order lines

Tejaxo Manufacturing (sample data) has eight order lines due for Tejaxo Customer this month:

LineDueSentQtyOTIFOTIF
1Day 5Day 5100 / 100YesYesYes
2Day 7Day 9200 / 200NoYesNo
3Day 8Day 8140 / 150YesNoNo
4Day 10Day 1050 / 50YesYesYes
5Day 12Day 11300 / 300YesYesYes
6Day 14Day 16110 / 120NoNoNo
7Day 15Day 1580 / 80YesYesYes
8Day 18Day 1860 / 60YesYesYes

Six of eight lines were on time (75%) and six were in full (75%), but only five were both: OTIF = 62.5%. By quantity, 98.1% of the ordered pieces arrived – a figure that looks excellent while three of eight lines disappointed the customer. Line 6 failed both ways; line 3 failed only because 10 pieces were short.

Finding the causes

OTIF is only useful if every miss carries a reason. Typical reasons:

Sorted by count, the reasons form a Pareto just like quality rejections – see how a defect Pareto works – and the top one or two are where improvement starts.

Order backlog: the misses that have not happened yet

OTIF looks back. The backlog looks forward: every open order line, grouped by how soon it is due. At day 20 of the month, the sample plant’s open lines look like this:

BucketLinesQty
Overdue (due date passed)3420
Due this week5900
Due next week4650
Later61,400
Total open183,370

The three overdue lines are already OTIF failures; the five due this week are the ones that can still be saved. A backlog review every morning – overdue first, then this week – with production and stores in the same room turns OTIF from a monthly report into a daily habit. Material for the lines due next week should already be checked against stock and open purchase orders – see how an MRP run finds shortfalls.

TAT to dispatch and order intake

Two more numbers complete the picture. TAT to dispatch – the days from order to dispatch – shows whether lead times are stable or creeping up. Order intake – new orders booked in the period against what was dispatched – shows whether the backlog is growing faster than the plant can ship. A growing backlog with a falling OTIF is the earliest warning that capacity or material planning needs attention.

How Tejaxo ERP handles it

In Tejaxo ERP the order-to-cash chain runs from CRM and quotation to a sales order with delivery schedules per line, a packing slip with finished-goods batches per order, the tax invoice and the receipt – each document pulled from the one before, so nothing is keyed twice. Sales reports include the order backlog, day-wise schedule, OTIF, TAT to dispatch, order intake, item-wise sales register, top customers and margin analysis, and customers can follow live order status. On the shop floor, work orders are created line-wise from sales orders and job cards are scheduled on each machine – see production planning.

Improving OTIF

  1. Commit dates the plant can meet. Check capacity and material before confirming, not after.
  2. Plan by line, not by order. Each line with its own date gets its own work order and material check.
  3. Review the backlog daily, overdue first.
  4. Record a reason for every miss, and act on the top reason each month.
  5. Share OTIF with key customers. A customer who sees the plant measuring itself honestly is more patient with the occasional miss.

Common mistakes

Next step

See the order backlog, OTIF and TAT to dispatch on your own orders in a free demo, or work out reorder points for the material behind them with the free reorder point calculator.

Frequently asked questions

What is OTIF?

On time, in full: the percentage of order lines delivered by the committed date with the full ordered quantity. A line that is late or short counts as a failure.

How is OTIF calculated?

OTIF % = order lines delivered on time and in full / order lines due x 100. For example, 5 of 8 lines on time and in full gives 62.5%.

What is the difference between OTIF and fill rate?

Fill rate (quantity) measures the share of ordered pieces delivered; OTIF measures the share of lines that were both complete and on time. Fill rate can be 98% while OTIF is much lower.

What is an order backlog?

All open order lines not yet delivered, usually grouped by due date – overdue, this week, next week and later – so the plant can act before lines become late.

Should the due date be changed when an order slips?

Not for OTIF. Keep the original committed date so the measure stays honest; record the revised date separately.

Does Tejaxo ERP report OTIF and backlog?

Yes. Sales reports include order backlog, day-wise schedule, OTIF, TAT to dispatch and order intake, from sales orders with delivery schedules per line.

Stay connected

ERP insights, product updates and automation tips for manufacturers.

You have been successfully subscribed! Oops! Something went wrong, please try again.
© 2017–2026 Tejaxo Technologies Pvt. Ltd. All rights reserved. Privacy policy · Sitemap · Contact