OEE Calculator: Availability, Performance and Quality in One Click

Enter one shift on one machine – shift length, breaks, downtime, ideal cycle time, pieces made and rejects – and see availability, performance, quality, OEE and utilisation instantly, with the biggest loss to fix first. Free, no sign-up, nothing is stored.

Enter one shift on one machine

Your result

Availability-
Performance-
Quality-
-OEE = Availability x Performance x Quality
Utilisation (run time / shift)-
Time lost to stops, speed and rejects-
Change any number to see your OEE.

How the OEE calculation works

Planned production time = shift length – planned breaks. Run time = planned production time – downtime.

  • Availability = run time / planned production time
  • Performance = (ideal cycle time x total pieces) / run time
  • Quality = good pieces / total pieces
  • OEE = availability x performance x quality, which is the same as good pieces x ideal cycle time / planned production time

A full worked example for a CNC machine, the six big losses and the common mistakes are explained in our guide: How to calculate OEE. To capture OEE automatically from production entries and machines, see machine data and OEE in the ERP and Tejaxo Automation. Also try our free FIFO, LIFO and weighted average stock valuation calculator and corrugated box calculator and reorder point and EOQ calculator.

Questions about OEE

OEE = Availability x Performance x Quality. Availability is run time divided by planned production time, performance is ideal cycle time x total count divided by run time, and quality is good count divided by total count.

Around 85% is often quoted as world class for discrete manufacturing, but most plants start lower. Track the trend for each machine and fix the lowest of the three factors first.

The ideal cycle time entered is slower than the machine really runs. Use the best rate the machine has actually achieved.

Utilisation shows how much of the shift the machine ran. OEE shows how much of the planned time produced good parts at full speed, so it also counts slow running and rejects.

Yes. In Tejaxo ERP, OEE is captured from production entries with downtime and rejection reasons, and CNC / VMC machines can send cycle counts, run and idle time straight into the ERP.

Measure OEE on every machine, every shift

See OEE, downtime by reason and rejections in Tejaxo ERP – from production entries or straight from your machines.

Stay connected

ERP insights, product updates and automation tips for manufacturers.

You have been successfully subscribed! Oops! Something went wrong, please try again.
© 2017–2026 Tejaxo Technologies Pvt. Ltd. All rights reserved. Privacy policy · Sitemap · Contact